South Quay Plaza
Details
Client: H&MV / Berkeley Homes
Services: 11kV UKPN primary Sub-station, IDNO 11kV substation, Full IDNO LV distribution
Year: 2019-20
SQP is a landmark development designed by world leading architects Foster + Partners
The Client required installation of one 11kV UKPN 9-panel primary Sub-station & one 11kV IDNO Sub-station. The Haddon team supplied HV Terminations, Testing & Commissioning, Scada & Metering. We also supplied mains and service distribution to 680 plots over 68 stories and 2 basement levels along with Multi Service Distribution Boards (MSDB) & Cut-out installation and Fusing & Linking.